Energy management is a hot topic right now. Our Networks team recently visited one of the world’s leaders in technology and digital transformation, working to build a sustainable energy future for all.

Customer challenge

To meet the growing demand for Ethernet connections, our customer wanted to standardize and extend its existing RJ45 copper and fiber Ethernet installation.
The main challenge was to successfully cover the entire site with RJ45 structured cabling, while the number of consumers (RJ45 Ethernet sockets) and their exact locations were not yet known with certainty.
In addition, the new network had to be deployed while keeping production running, and without disrupting site personnel.

Solution implemented by our teams

Our teams designed and deployed the entire passive F.O. and RJ45 copper network architecture.

This study, carried out in close collaboration with the customer, was based on a global number of RJ45 connections distributed by sector: 600 connections spread over an area of around 6,500m².

Some key figures for this project :

460 hours of site design and supervision

  • Network architecture study and design
  • Design and production of a layout plan for RJ45 zone boxes
  • Design and production of layout plans for new network cabinets
  • Sizing new cable trays
  • Creation of a standard label showing the location of each zone box and RJ45 connector.
  • Drafting of test reports for fiber optic and copper certifications

160 hours of CAD (Computer-Aided Design)

  • Layout plan for RJ45 consolidation boxes
  • Production of electrical and DATA drawings for new cabinets
  • DATA cable list creation

2900 hours of site work

  • Construction of 3 new 19″ DATA cabinets, equipped with UPS.
  • Installation of 1,000 meters of new walkways.
  • Laying 1,300 meters of single-mode fiber optic cable, divided into 7 separate segments.
  • Installation of 30,000 meters of RJ45 Cat7a SFTP POE++ 1500MHz cable
  • 384 fiber optic connections
  • Installation of 120 RJ45 consolidation boxes
  • Connection of 1200 RJ45 Cat6A SFTP connectors
  • Deployment of 23 WIFI access points
  • Fiber optic and copper segment validation tests to ISO/IEC 11801 Class Ea standards

6-month project

Gain for the customer

The proposed technical solution, combined with the use of RJ45 consolidation boxes, enables modularity and flexible management of structured cabling.

We succeeded in deploying 600 RJ45 connection points throughout the factory, without knowing exactly where the users would end up, and without disturbing the production units that were still running, to the customer’s complete satisfaction.

Technord news

More articles to discover.

Renovation and relocation of a machine park

Find out how our Process Control teams worked on the machinery of a global tire manufacturer. Customer challenge During the renovation and relocation of a machine park, a large number of operatorinterventions had to be maintained. For our customer, it was necessary...

Syscade: feedback on an automation / process control project

The Syscade project, which recently won the jury and public awards at the Wap'Innov competition, involves developing a mobile laboratory for inspecting and characterizing nuclear waste. Background to the Syscade project For many years, a great deal of radioactive...

Wap’Innov competition: Technord wins two awards

By creating a project in collaboration with DSI, aimed at inspecting and characterizing nuclear waste, we were rewarded by the public and by the jury of the Wap'Innov competition. Wap'Innov, a competition that rewards innovators in Picardy's Walloon region Wap'Innov...

An IoT solution for wireless data recovery

Our IoT department has deployed a solution at the site of a major road construction company in Belgium. Customer challenge Initially, our customer had a proprietary solution that uploaded data to an external platform. Unfortunately, their service provider went...

Pairi Daiza adapts to new energy challenges

Pairi Daiza, the superb animal park in Picardy Wallonia, voted best zoo in Europe, has entrusted Technord with the adaptation of its Medium Voltage power supplies. Customer challenge The existing 5MVA connection was insufficient for the development of the park and the...